A repair BOM calling for ispPAC-POWR1014-01T48I identifies a specific Lattice Power Manager II ordering number. For a legacy board, the first purchasing decision is whether the assembly specification permits a change of lead finish. Keep the original code on the RFQ until the owner of that specification records the answer.
Look for the N in the proposed ordering number
The affected-part workbook for PCN 02A-15 names ispPAC-POWR1014-01T48I in column C of row 2180. That row identifies TQFP, 48 leads and a SnPb finish for the discontinued part. It lists ispPAC-POWR1014-01TN48I in the alternative field. A distributor’s shortened POWR1014 label hides precisely the distinction this notice asks you to review.
Read the two deadlines separately
Lattice issued the notice on 2015-06-23. The ordering cutoff was 2015-12-23 and the last shipment milestone was 2016-12-30. Preserve both dates in a service BOM. A later offer for the original code needs its own lot history, storage evidence and commercial terms.
Decide who can approve a finish change
The v3 workbook dated 2015-08-12 marked pinout, voltage and SnPb assembly compatibility as yes for the historical alternative. Record those three flags verbatim in the change request, then ask the board owner to check the substitute’s current ordering status, pin table, applicable thermal profile, material restrictions and programmed configuration. The notice cannot certify the process used to repair this particular board.
PCN 02A-15 — manufacturer withdrawal notice · Original affected-order-code workbook, v3
Show how to compare an offer with the full order code

Transcribe both complete ordering numbers, mark the first difference and ask for its manufacturer definition. Keep the identity decision separate from a board substitution approval.
- Capture the existing power-up sequence before changing a programmed part
- List the assembly files needed by the process reviewer
- Check the complete order-code text
- Prepare quantities for the maintenance BOM
- Find the manufacturer notice for another order code
If your repair specification locks the original finish, request the exact T48I order code. If it permits a change, send TN48I for a separate engineering review with the assembly profile and configuration revision. Ask for quantities and traceability on separate lines.